The Elites Network for Sustainable
Development (ENetSuD), a Kwara-based Civil Society Organization (CSO)
reputed for its #FollowKwaraMoney activities, has queried some
₦53,511,672 in the Comprehensive Rehabilitation and Construction of
Additional Facilities in the Patigi Secondary School project of Kwara
State Government (KWSG) whose contract sum is ₦164,042,340. This was
contained in the Social Audit report submitted by ENetSuD to Governor
AbdulRahman AbdulRazaq dated 5th January, 2021.
It will be recalled that Kwara Social Audit, the first of its kind in
the country, was initiated and proposed by the AbdulRahman-led Kwara
State Government and has ENetSuD as the first (and presently only) CSO
executing the audit in the public interest. In the Social Audit
partnership between ENetSuD and KWSG, the latter is willingly releasing
all the required contract documents to the former despite the
non-domestication of the Freedom of Information (FOI) Act by the State
Assembly.
ENetSuD maintains its belief that the Social Audit is a step forward as
it offers a useful opportunity for the public to interrogate projects
being executed with public funds.
In the audit report signed by its Coordinator (Dr. Alagbonsi
Abdullateef), ENetSuD divided its findings into 2 parts namely: the
examination of the Bill of Quantity (BoQ) and the site evaluation of the
works done by the contractor.
Concerning the examination of the BoQ, ENetSuD berated the
professionalism in the preparation of the BoQ and told the Governor that
the contract sum of the project appears to have been inflated in the
BoQ by at least Thirty-One Million, Nine Hundred and Eighty Thousand,
Seventy Hundred and Ninety-Nine Naira (₦31,980,799) due to the insertion
of irrelevant items. “A sum of Twenty-Five Million, Four Hundred and
Ninety-Nine Thousand, Eight Hundred and Seventy Naira (₦25,499,870) was
inserted without justifiable cause into the bills of 21 project units
for progress photographs, distance projects, vetting fee, monitoring,
inspection and evaluation, withholding tax (WHT), and development levy.
Another sum of Six Million, Four Hundred and Eighty Thousand, Nine
Hundred and Twenty-Eight Naira (₦6,480,928) was inserted into the bill
summary for General Contingency, General Preliminary, and Monitoring,
Inspection and Evaluation. The contingency and preliminary have already
been provided for in each of the components, while the monitoring and
evaluation is an odd item that should not be in the Bill of the
contractor. Thus, they are not supposed to be added to the final
contract sum in the bill summary, ENetSuD told the Governor.
Concerning the site evaluation of the works done by the contractor,
ENetSuD told the Governor that various items in the BoQ worth Twenty-One
Million, Five Hundred and Thirty Thousand, Eight Hundred and
Seventy-Four Naira (₦21,530,874) were yet to be executed by the
contractor as at 20th September, 2020 when its audit was concluded.
“Using the same rate as approved in the BoQ and based on our
re-assessment and re-evaluation of the works done on the site by the
contractor, various items worth ₦21,530,874 have not been executed in
the site when we visited it. This is contrary to the provisions made for
them in the BoQ”, ENetSuD said.
Signed
Usman Radhiyyat Taiye (Mrs),
Deputy Coordinator (Administration),
Elites Network for Sustainable Development (ENetSuD)
Monday, 11 January 2021
ENetSuD queries ₦53.5 million on Patigi Secondary School Project
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment